Escondido - New Multi-Purpose and Administration Building - Progress week of 12/11

El Building:

  • Exterior form work and final grading prior to flatwork pours continues this week. Off haul for dirt in dump trucks as well as skid steer and small excavator use will continue for the balance of the week. Typical for equipment running and beeping. Light hand tool use for additional noise generation is possible.

MPR Building:

  • Framing activity continues. Scissor lifts, nail guns, saws and hammers for noise with relative consistency throughout the day. Occasional use of the gradall near the Tower House for material moving (diesel noise and beeping)
  • Fire water line trenching and compaction has been completed along the Bing fence line. The project will focus on the building footprint now through to late Spring.