Escondido - New Multi-Purpose and Administration Building - Progress week of 12/18
EL Building:
- Form work and reinforcement continues, mostly hand tool use and intermittent saw use for both metal and wood throughout the week.
- Small concrete pours are possible depending upon the weather throughout the week. Likely to take place the following week. Concrete pump and truck noise in small windows of time when this takes place.
MPR Building:
- Framing activity continues. Scissor lifts, nail guns, saws and hammers for noise. Occasional use of the gradall near the Tower House for material moving. (diesel noise and beeping)
- Some rough-in electrical work will be ongoing as well which may involve some metal material cutting for short durations.