Irrigation work continues throughout the week, small skid steer and excavator use throughout the day. Minor beeping and idling noise expected.
Grade all use towards the end of the week relocating some landscaping items, expect idling and beeping for several hours likely mid week.
Exterior painting will be ongoing early in the week to completion.
Final cleaning will be completed this week, no noise impacts.
MPR Building:
Sheathing and blocking continue in multiple areas of the project, with hand tool use to include compressors, nail guns, saws and hammers running consistently throughout the day.
Some grade-all use for small windows of time for hoisting material to the roof will continue throughout the week, along with scissor lift beeping throughout the day.
Exterior insulation will begin using scaffolding followed by sheathing and nail off activities. This will be mostly hand tool and nail gun use throughout the week.
Steel columns for the canopy will be erected this week, which will bring some grinding and welding noise early in the week for about one day.