Escondido - New Multi-Purpose and Administration Building - Progress week of 3/11

EL Building:

  • Punchlist items are being recorded and addressed across the entire new Enrichment lab area, no noise impacts expected.
  • Exterior painting is ongoing this week into next week, light compressor noise when spraying likely.
  • Irrigation trenching is almost complete and soils testing will begin next week prior to landscape installation.
  • Commissioning 90% complete

MPR/Admin Building:

  • Canopy area joist work is nearing completion, and sheathing is ongoing.  Expect frequent nail gun noise and minor compressor noise throughout the day.
  • Fire sprinkler main and branch line nearing completion in the MPR space.
  • Roof drains have been installed.
  • Ongoing blocking throughout the space, will involve hand tool and saw use throughout the day.