Irrigation work is finalizing their connections for the drip system.
Landscaping soil tilling continues throughout the courtyard and back of building areas in preparation for planting. Light excavator use to be expected.
Second coat of paint on the exterior is ongoing and nearing completion.
MPR/Admin Building:
Liquid waterproofing at the roof level has been completed.
Interior wall framing is 95% complete.
Blocking is ongoing throughout the project and exterior sheathing will be completed this week.