Landscaping work will be ongoing throughout the week, will be mostly hand tool use without noise impacts.
Grade- all use to relocate boulders in and around the EL building will take place during the week, expect idling and beeping for several hours likely mid-week.
Final commissioning to take place on Wednesday.
Possible fire alarm testing on campus during the afternoon of Wednesday 3/27.
MPR/Admin Building:
Blocking and backing work continues, expect hand tool, saw, nail gun and scissor lift use throughout the week.
Electrical and Plumbing rough in continues throughout the week, no noise impacts anticipated.
Fire Sprinkler installation will complete the main phase of installation by Tuesday this week.
Final trenching and compaction work for seat walls as well as form and bracing work will take place over several days mid-week. Small excavator and small dump use involving some idling and beeping.
Potential to begin some site work grading around the perimeter of the MPR building, would involve fairly consistent equipment use and beeping throughout the day beginning mid week.